SAP
C_ACTIVATE13 · Question #33
What technique helps a scrum team to prioritize a large, flat backlog?
The correct answer is A. User story mapping. See the full explanation below for the reasoning.
Question
What technique helps a scrum team to prioritize a large, flat backlog?
Options
- AUser story mapping
- BRetrospective
- CPlanning poker
- DFit/gap analysis
How the community answered
(21 responses)- A81% (17)
- B10% (2)
- C5% (1)
- D5% (1)
Community Discussion
No community discussion yet for this question.