Which of the following are part of the 10 SAP quality principle? There are 2 correct answers to this question
The correct answer is A. Start scoping early C. Achieve production readiness. See the full explanation below for the reasoning.
Question
Which of the following are part of the 10 SAP quality principle? There are 2 correct answers to this question
Options
- AStart scoping early
- BUse standard functionality optionally
- CAchieve production readiness
- DPlan phase at a time
How the community answered
(51 responses)- A84% (43)
- B6% (3)
- D10% (5)