Which artifacts are created within application design and configuration workstream in the explore Phase of the "New implementation of SAP S/4HANA"? There are 3 correct answers to this question
The correct answer is B. Roles and authorizations management concept C. Delta requirements list-register D. Detailed design-business process. See the full explanation below for the reasoning.
Question
Which artifacts are created within application design and configuration workstream in the explore Phase of the "New implementation of SAP S/4HANA"? There are 3 correct answers to this question
Options
- AProject procedure-mock-up modeling
- BRoles and authorizations management concept
- CDelta requirements list-register
- DDetailed design-business process
- EOrganisation structure specification
How the community answered
(53 responses)- A6% (3)
- B83% (44)
- E11% (6)