BIMF.EN · Question #44
What is not a subject of the process Transition?
The correct answer is B. end users. End users (B) are not a subject of the Transition process because Transition focuses on moving services from development into production - handling planning, testing, deployment, and formalization of agreements. End users become the primary concern during Service Operation…
Question
What is not a subject of the process Transition?
Options
- Acontracts
- Bend users
- Ctransition plan
How the community answered
(41 responses)- A10% (4)
- B83% (34)
- C7% (3)
Explanation
End users (B) are not a subject of the Transition process because Transition focuses on moving services from development into production - handling planning, testing, deployment, and formalization of agreements. End users become the primary concern during Service Operation, which is where live service delivery and user interaction occur.
Contracts (A) are a valid Transition subject - supplier and underpinning contracts often need to be established or updated when a new or changed service is being deployed, making them part of the Transition scope.
Transition plan (C) is arguably the core artifact of the process - it governs how the service change is organized, scheduled, and executed, so it is absolutely a Transition subject.
Memory tip: Think of it as a relay race - Transition hands off the baton. The crowd (end users) only shows up after the handoff, in Operation. Everything on the track (contracts, plans, testing) belongs to Transition; the audience does not.