Which activity belongs to the process End user support?

The correct answer is C. communicating with end users. Communicating with end users (C) is the correct answer because End user support is fundamentally about maintaining an ongoing relationship with users - answering their questions, addressing concerns, and providing assistance during daily use of systems. Direct communication is…

Operation Management

Question

Which activity belongs to the process End user support?

Options

  • Amaking a planning for a new release
  • Bperforming a user acceptance test
  • Ccommunicating with end users

How the community answered

(36 responses)
  • A
    8% (3)
  • B
    19% (7)
  • C
    72% (26)

Explanation

Communicating with end users (C) is the correct answer because End user support is fundamentally about maintaining an ongoing relationship with users - answering their questions, addressing concerns, and providing assistance during daily use of systems. Direct communication is the core activity of this process.

Option A (making a planning for a new release) belongs to a change or release management process, not end user support - it is forward-looking and technical, focused on deployment rather than helping existing users.

Option B (performing a user acceptance test) is part of the testing or transition phase of a project, where users validate that a system meets requirements before go-live - this is a one-time quality activity, not ongoing support.

Memory tip: Think of "End user support" as the helpdesk role - the moment something is live and a user picks up the phone or sends a ticket, you are in End user support territory. If the activity happens before go-live (testing, planning releases), it belongs elsewhere.

Topics