What is not an activity of the Change management process?
The correct answer is C. requesting an impact analysis from an IT service provider. Option C is correct because requesting an impact analysis from an external IT service provider is not a Change Management activity - impact analysis is conducted internally by the Change Management process itself (often through a Change Advisory Board), not outsourced to a…
Question
What is not an activity of the Change management process?
Options
- Aanalysis of the necessity of a suggested change
- Bdetermining the impact of a suggested change to other business processes
- Crequesting an impact analysis from an IT service provider
How the community answered
(30 responses)- A20% (6)
- B7% (2)
- C73% (22)
Explanation
Option C is correct because requesting an impact analysis from an external IT service provider is not a Change Management activity - impact analysis is conducted internally by the Change Management process itself (often through a Change Advisory Board), not outsourced to a service provider. That responsibility belongs to supplier or contract management processes.
Option A is wrong because evaluating whether a proposed change is actually necessary is a fundamental first step in Change Management - unnecessary changes introduce risk with no benefit, so this assessment is always performed.
Option B is wrong because assessing how a change affects other business processes (cross-functional impact analysis) is a core Change Management responsibility, ensuring no downstream processes are unintentionally disrupted.
Memory tip: Think of Change Management as an internal gatekeeper - it owns the analysis (necessity, risk, impact) before approving or rejecting changes. The moment you "request" something from an external party, you've stepped outside the process boundary.