You need to consider the underlined segment to establish whether it is accurate. The Burnup widget measures the elapsed time from creation of work items to their completion. Select "No adjustment requ

The correct answer is B. Lead time. https://docs.microsoft.com/en-us/azure/devops/report/dashboards/cycle-time-and-lead- time?view=azure-devops

Submitted by paula_co· Mar 6, 2026Implement an instrumentation strategy

Question

You need to consider the underlined segment to establish whether it is accurate. The Burnup widget measures the elapsed time from creation of work items to their completion. Select "No adjustment required" if the underlined segment is accurate. If the underlined segment is inaccurate, select the accurate option.

Options

  • ANo adjustment required.
  • BLead time
  • CTest results trend
  • DBurndown

How the community answered

(21 responses)
  • B
    86% (18)
  • C
    5% (1)
  • D
    10% (2)

Explanation

https://docs.microsoft.com/en-us/azure/devops/report/dashboards/cycle-time-and-lead- time?view=azure-devops