AGILEPM-PRACTITIONER · Question #75

The Web Content Manager has provided the Web Developer with a mock up of the 'Contact Us' page, to be created for the new coffee bar insurance product. When producing the code, the Web Developer has…

The correct answer is D. Discuss the issue with the Web Developer and decide what action is. The most constructive and collaborative action the Web Content Manager should take is: D . Discuss the issue with the Web Developer and decide what action is required to change this Direct communication and collaboration between the Web Content Manager and the Web Developer are…

AgilePM Roles and Responsibilities

Question

The Web Content Manager has provided the Web Developer with a mock up of the 'Contact Us' page, to be created for the new coffee bar insurance product. When producing the code, the Web Developer has created a button that reads 'Delete' instead of 'Cancel'. What action should the Web Content Manager take?

Options

  • APrepare a defence for when the problem is identified, ensuring the
  • BHide the problem and hope that this detail can be changed at a later date.
  • CRaise an issue to the Project Manager when the solution is deployed.
  • DDiscuss the issue with the Web Developer and decide what action is

How the community answered

(51 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    2% (1)
  • D
    92% (47)

Explanation

The most constructive and collaborative action the Web Content Manager should take is: D . Discuss the issue with the Web Developer and decide what action is required to change this Direct communication and collaboration between the Web Content Manager and the Web Developer are essential in Agile environments to promptly address misunderstandings or mistakes. Discussing the issue openly allows for a quick resolution and ensures that the final product aligns with the project's requirements. This approach fosters a positive working relationship, encourages shared responsibility for the project's success, and avoids unnecessary delays or conflicts.

Topics

#issue management#team communication#quality#problem resolution