AGILEPM-PRACTITIONER · Question #77
AGILEPM-PRACTITIONER Question #77: Real Exam Question with Answer & Explanation
The correct answer is C. Attend the Daily Stand-up and discuss any problems at the end.. To lead the Solution Development Team effectively during the first Structured Timebox, the Project Attending the Daily Stand-up meetings allows the Project Manager to stay informed about the team's progress, challenges, and any blockers they might be facing. It offers an opportun
Question
Options
- AMaintain a tight control on progress, recording all discussions and making
- BThe Project Manager should do nothing during a Timebox.
- CAttend the Daily Stand-up and discuss any problems at the end.
- DUpdate the Team Board with a summary of team progress and the current
Explanation
To lead the Solution Development Team effectively during the first Structured Timebox, the Project Attending the Daily Stand-up meetings allows the Project Manager to stay informed about the team's progress, challenges, and any blockers they might be facing. It offers an opportunity for the Project Manager to provide support, guidance, and decision-making where necessary, without disrupting the team's autonomy and self-organization. This approach encourages open communication, quick resolution of issues, and maintains the Agile principle of collaboration and continuous improvement. Discussing problems at the end of the meeting ensures that any issues are addressed promptly, keeping the Timebox on track.
Community Discussion
No community discussion yet for this question.