nerdexam
APMG-International

AGILEPM-PRACTITIONER · Question #32

AGILEPM-PRACTITIONER Question #32: Real Exam Question with Answer & Explanation

The correct answer is A. Facilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox. See the full explanation below for the reasoning.

Question

The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and to know who should be where. Some of the contractors have started to turn up late to the site. Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations. Answer the following questions about motivating the contractor teams according to Agile Project Management. How should the Project Manager encourage the resources to operate more successfully?

Options

  • AFacilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox
  • BHold a separate Daily Stand-up meeting for contractors only.
  • CProvide a detailed plan of activity for each contractor team.
  • DSchedule the electrical and plumbing teams so that they work on different Timeboxes.

Community Discussion

No community discussion yet for this question.

Full AGILEPM-PRACTITIONER Practice