AD0-E907 · Question #48
What data can be tracked using the resource planner? (Select two.)
The correct answer is B. Planned hours D. Allocation percentages. Planned hours (B) and allocation percentages (D) are the two data types native to a resource planner because its core purpose is forward-looking capacity management - showing how much time is scheduled for each resource and what proportion of their availability is committed to…
Question
What data can be tracked using the resource planner? (Select two.)
Options
- AActual hours worked
- BPlanned hours
- CRisk scores
- DAllocation percentages
How the community answered
(23 responses)- A13% (3)
- B83% (19)
- C4% (1)
Explanation
Planned hours (B) and allocation percentages (D) are the two data types native to a resource planner because its core purpose is forward-looking capacity management - showing how much time is scheduled for each resource and what proportion of their availability is committed to work.
Why the distractors are wrong:
- A (Actual hours worked) is captured in timesheets or time-tracking tools, not the resource planner, which is planning-focused rather than actuals-focused.
- C (Risk scores) belong in a risk register or risk matrix - an entirely separate project artifact unrelated to resource allocation.
Memory tip: Think of the resource planner as a schedule blueprint - it shows what you plan (hours) and how much of someone's capacity is claimed (percentage). Anything measuring what already happened (actuals) or assessing uncertainty (risk) lives in a different tool.