Which metric in Workfront Resource Management provides visibility into team utilization?

The correct answer is B. Allocation percentage. Allocation percentage is the correct metric because it directly shows what portion of a resource's available capacity is assigned to work - giving managers a clear picture of whether team members are over-allocated, under-utilized, or balanced. Planned variance (A) measures the…

Workfront Object Model

Question

Which metric in Workfront Resource Management provides visibility into team utilization?

Options

  • APlanned variance
  • BAllocation percentage
  • CTask duration
  • DEstimated completion date

How the community answered

(26 responses)
  • A
    19% (5)
  • B
    69% (18)
  • C
    4% (1)
  • D
    8% (2)

Explanation

Allocation percentage is the correct metric because it directly shows what portion of a resource's available capacity is assigned to work - giving managers a clear picture of whether team members are over-allocated, under-utilized, or balanced. Planned variance (A) measures the difference between planned and actual work, relating to schedule/cost tracking rather than utilization. Task duration (C) is simply a time estimate for a task and says nothing about how loaded a person is. Estimated completion date (D) predicts when work will finish, not how much of someone's capacity is consumed.

Memory tip: Think of "allocation percentage" like a battery indicator for your team - it shows how "charged up" (utilized) each person is, from 0% (idle) to 100%+ (overloaded).