What are key components of resource management in Workfront? (Select two.)
The correct answer is A. Resource pool configuration C. Capacity planning. Resource pools and capacity planning are the two pillars of Workfront's resource management system: resource pools group users by role or availability so managers can assign them to projects, while capacity planning (via the Resource Planner and Workload Balancer) lets you…
Question
What are key components of resource management in Workfront? (Select two.)
Options
- AResource pool configuration
- BTask constraints
- CCapacity planning
- DAgile boards
How the community answered
(46 responses)- A83% (38)
- B13% (6)
- D4% (2)
Explanation
Resource pools and capacity planning are the two pillars of Workfront's resource management system: resource pools group users by role or availability so managers can assign them to projects, while capacity planning (via the Resource Planner and Workload Balancer) lets you visualize and balance workload against available hours. Task constraints (B) control scheduling behavior like fixed dates and dependencies - they affect when work happens, not who does it. Agile boards (D) are a project execution view for iterative work and have no direct connection to resource allocation.
Memory tip: Think "R-C = Resource Control" - Resource pools + Capacity planning = the two tools that let you control who does what and whether they're overloaded.