A portfolio manager needs to identify whether projects within a portfolio meet specific strategic criteria. What approach should they take?

The correct answer is A. Create a custom dashboard to filter projects based on criteria. Option A is correct because a custom dashboard with filters is the most direct and scalable tool for evaluating multiple projects against specific strategic criteria simultaneously - it lets a portfolio manager apply consistent, repeatable criteria across an entire portfolio at…

Reporting and Dashboards

Question

A portfolio manager needs to identify whether projects within a portfolio meet specific strategic criteria. What approach should they take?

Options

  • ACreate a custom dashboard to filter projects based on criteria
  • BReview each project's financial summary
  • CUse a predefined Gantt chart to track task durations
  • DGenerate a workload balancer report

How the community answered

(16 responses)
  • A
    88% (14)
  • B
    6% (1)
  • D
    6% (1)

Explanation

Option A is correct because a custom dashboard with filters is the most direct and scalable tool for evaluating multiple projects against specific strategic criteria simultaneously - it lets a portfolio manager apply consistent, repeatable criteria across an entire portfolio at a glance.

  • B is wrong because a financial summary only covers budget/cost data, not strategic alignment criteria like business objectives or risk tolerance.
  • C is wrong because a Gantt chart tracks task timelines and dependencies - it answers when things happen, not whether projects meet strategic goals.
  • D is wrong because a workload balancer report focuses on resource capacity and team allocation, not strategic fit.

Memory tip: Think of the word "criteria" as your clue - criteria require filtering, and filtering requires a dashboard. Gantt = time, workload = people, financial = money; only a dashboard handles strategic criteria.

Topics

#portfolio management#custom dashboard#strategic criteria#project filtering