AD0-E907 · Question #77
How can a project manager view resource availability across multiple projects?
The correct answer is B. By generating a resource utilization report. Generating a resource utilization report (B) gives a project manager a consolidated view of how resources are allocated and available across multiple projects simultaneously - it's specifically designed to surface capacity gaps, overallocations, and idle time in one place. Why…
Question
How can a project manager view resource availability across multiple projects?
Options
- ABy using project timelines
- BBy generating a resource utilization report
- CBy reviewing baseline comparisons
- DBy checking task-level predecessors
How the community answered
(24 responses)- A17% (4)
- B75% (18)
- C4% (1)
- D4% (1)
Explanation
Generating a resource utilization report (B) gives a project manager a consolidated view of how resources are allocated and available across multiple projects simultaneously - it's specifically designed to surface capacity gaps, overallocations, and idle time in one place.
Why the distractors are wrong:
- A (Project timelines) show task scheduling and sequencing, not resource capacity or availability.
- C (Baseline comparisons) measure performance against the original plan (scope, cost, schedule) - not resource load.
- D (Task-level predecessors) reveal task dependencies and sequencing logic, which has nothing to do with who is available to do the work.
Memory tip: Think "utilization = usage of people." If you need to know whether your people are free, you need a resource utilization report. Any answer about timelines, baselines, or predecessors is about tasks and schedules, not human capacity.