AD0-E907 · Question #77

How can a project manager view resource availability across multiple projects?

The correct answer is B. By generating a resource utilization report. Generating a resource utilization report (B) gives a project manager a consolidated view of how resources are allocated and available across multiple projects simultaneously - it's specifically designed to surface capacity gaps, overallocations, and idle time in one place. Why…

Reporting and Dashboards

Question

How can a project manager view resource availability across multiple projects?

Options

  • ABy using project timelines
  • BBy generating a resource utilization report
  • CBy reviewing baseline comparisons
  • DBy checking task-level predecessors

How the community answered

(24 responses)
  • A
    17% (4)
  • B
    75% (18)
  • C
    4% (1)
  • D
    4% (1)

Explanation

Generating a resource utilization report (B) gives a project manager a consolidated view of how resources are allocated and available across multiple projects simultaneously - it's specifically designed to surface capacity gaps, overallocations, and idle time in one place.

Why the distractors are wrong:

  • A (Project timelines) show task scheduling and sequencing, not resource capacity or availability.
  • C (Baseline comparisons) measure performance against the original plan (scope, cost, schedule) - not resource load.
  • D (Task-level predecessors) reveal task dependencies and sequencing logic, which has nothing to do with who is available to do the work.

Memory tip: Think "utilization = usage of people." If you need to know whether your people are free, you need a resource utilization report. Any answer about timelines, baselines, or predecessors is about tasks and schedules, not human capacity.

Topics

#resource utilization#resource availability#multi-project#resource report

Community Discussion

No community discussion yet for this question.