AD0-E907 · Question #103
A team is consistently overallocated due to overlapping projects. How should the project manager address this?
The correct answer is B. Use the capacity planner to reallocate resources. Using the capacity planner to reallocate resources (B) is the correct approach because it directly addresses the root cause - overallocation - by analyzing where each resource is committed and redistributing work across people or time in a data-driven way, without disrupting…
Question
A team is consistently overallocated due to overlapping projects. How should the project manager address this?
Options
- AReduce the number of active projects
- BUse the capacity planner to reallocate resources
- CEnable automatic resource leveling
- DIncrease resource working hours
How the community answered
(48 responses)- A13% (6)
- B77% (37)
- C4% (2)
- D6% (3)
Explanation
Using the capacity planner to reallocate resources (B) is the correct approach because it directly addresses the root cause - overallocation - by analyzing where each resource is committed and redistributing work across people or time in a data-driven way, without disrupting the overall project portfolio.
- A (Reduce active projects) is too drastic and may not be within the PM's authority; the problem is poor allocation, not the number of projects itself.
- C (Automatic resource leveling) is a tool feature, not a strategy - it adjusts task schedules based on existing assignments but doesn't solve the underlying allocation imbalance across projects.
- D (Increase working hours) treats overallocation by adding unsustainable effort rather than fixing the structural problem, and risks burnout.
Memory tip: Think of the capacity planner as your "traffic control tower" - when lanes are congested (overallocated), you reroute traffic (reallocate resources), not close roads or force drivers to speed.