You are a portfolio manager in an organization that uses Project Server 2013. You plan to review the milestones status of a project named Proj1. You need to create a graphical view of all milestones…

The correct answer is C. Create a Project view named Milestones with the Task Name, Start, and Finish fields. See the full explanation below for the reasoning.

Question

You are a portfolio manager in an organization that uses Project Server 2013. You plan to review the milestones status of a project named Proj1. You need to create a graphical view of all milestones of Proj1 that allows you to see the Start and Finish dates of each milestone. You need to accomplish this goal in the least amount of time. What should you do?

Options

  • AOpen Microsoft Visio and make a data connection against the Project Server database.
  • BOpen Microsoft Excel and make a data connection against the Project Server database.
  • CCreate a Project view named Milestones with the Task Name, Start, and Finish fields.
  • DCreate a Microsoft SQL Server Reporting Services (SSRS) report with a data connection

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    18% (9)
  • C
    71% (36)
  • D
    8% (4)