Microsoft
74-344 · Question #92
You are a program manager in the Project Management Office (PMO) of an organization that is implementing Project Server 2013. You plan to include five of your organization's departments in the first…
The correct answer is C. For each department, create one enterprise project template (EPT), one Project Site. See the full explanation below for the reasoning.
Question
You are a program manager in the Project Management Office (PMO) of an organization that is implementing Project Server 2013. You plan to include five of your organization's departments in the first rollout of Project Server 2013. You need to develop a project creation process that meets the following requirements:
- Each department must have its own Project Site template.
- Each department must have its own Project Schedule template.
- The project creation process needs to be developed in the least
amount of time. What should you do?
Options
- ACreate five projects, one for each department.
- BCreate five Microsoft SharePoint sites and five projects, one for each department.
- CFor each department, create one enterprise project template (EPT), one Project Site
- DCreate a single Microsoft SharePoint site and one project for each department, and then
How the community answered
(30 responses)- A3% (1)
- B10% (3)
- C83% (25)
- D3% (1)
Community Discussion