74-344 · Question #87
You work as a project manager in an organization that uses Project Server 2013. All project managers belong to the Project Management Office (PMO) and use Project Professional 2013. A member of the…
The correct answer is C. Open the schedule in Project Professional 2013 and change the status manager for all tasks. See the full explanation below for the reasoning.
Question
You work as a project manager in an organization that uses Project Server 2013. All project managers belong to the Project Management Office (PMO) and use Project Professional 2013. A member of the PMO is responsible for initiating a new project schedule in Project Server and fills in critical project-level fields such as Sponsor and Project Budget. The PMO publishes the new project and then, through email, instructs the project manager to complete a detailed schedule. You are responsible for planning and managing the schedule, including approving task updates from team members. After speaking to your team members, you discover that task updates have been submitted, but you are not receiving them; instead, these updates are going to the person in the PMO who initially set up the schedule. You need to solve this problem. What should you do?
Options
- AInstruct the person in the PMO to open the schedule in Project Professional 2013 and
- BInstruct the person in the PMO to open the schedule in Project Professional 2013 and
- COpen the schedule in Project Professional 2013 and change the status manager for all tasks
- DOpen the schedule in Project Professional 2013 and change the assignment owner for all
How the community answered
(25 responses)- A8% (2)
- B4% (1)
- C84% (21)
- D4% (1)
Community Discussion
No community discussion yet for this question.