nerdexam
Microsoft

74-344 · Question #87

74-344 Question #87: Real Exam Question with Answer & Explanation

Sign in or unlock 74-344 to reveal the answer and full explanation for question #87. The question stem and answer options stay visible for context.

Question

You work as a project manager in an organization that uses Project Server 2013. All project managers belong to the Project Management Office (PMO) and use Project Professional 2013. A member of the PMO is responsible for initiating a new project schedule in Project Server and fills in critical project-level fields such as Sponsor and Project Budget. The PMO publishes the new project and then, through email, instructs the project manager to complete a detailed schedule. You are responsible for planning and managing the schedule, including approving task updates from team members. After speaking to your team members, you discover that task updates have been submitted, but you are not receiving them; instead, these updates are going to the person in the PMO who initially set up the schedule. You need to solve this problem. What should you do?

Options

  • AInstruct the person in the PMO to open the schedule in Project Professional 2013 and
  • BInstruct the person in the PMO to open the schedule in Project Professional 2013 and
  • COpen the schedule in Project Professional 2013 and change the status manager for all tasks
  • DOpen the schedule in Project Professional 2013 and change the assignment owner for all

Unlock 74-344 to see the answer

You've previewed enough free 74-344 questions. Unlock 74-344 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full 74-344 Practice