nerdexam
Microsoft

74-344 · Question #86

You are a project manager for a company that uses Project Server 2013 in Project Server Permission Mode. You have been managing a project for several months. You go on vacation, and you delegate…

The correct answer is D. Publish the task updates from the Status History page. See the full explanation below for the reasoning.

Question

You are a project manager for a company that uses Project Server 2013 in Project Server Permission Mode. You have been managing a project for several months. You go on vacation, and you delegate your project management responsibility to one of your coworkers. Your coworker accepts multiple status updates on the project. When you return, you notice that no project updates are visible in Project Web App (PWA), and there are no status updates awaiting approval. You need to ensure that the previously accepted status updates are visible in PWA. What should you do?

Options

  • ASet the date range in the Approval's page to include last week's updates.
  • BHave your team resubmit last week's status updates.
  • CHave your team resubmit last week's timesheet updates.
  • DPublish the task updates from the Status History page.

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    14% (5)
  • C
    6% (2)
  • D
    78% (28)

Community Discussion

No community discussion yet for this question.

Full 74-344 Practice