74-344 · Question #34
You are a project manager for an organization that uses Project Server 2013. After performing a review of all the risks created by your project team for one of your projects, you realize that the…
The correct answer is B. Open your project in Project Web App (PWA). See the full explanation below for the reasoning.
Question
You are a project manager for an organization that uses Project Server 2013. After performing a review of all the risks created by your project team for one of your projects, you realize that the risks are not linked to their related tasks. You need to link the risks to their related tasks. What should you do?
Options
- AOpen each risk, select the Attach file option, and then select the name of the related task.
- BOpen your project in Project Web App (PWA).
- CCreate a new field for the Risk content type in SharePoint and name it "task name".
- DOpen each risk and copy and paste its name into the Notes field in the task page.
How the community answered
(16 responses)- A6% (1)
- B81% (13)
- D13% (2)