You are a project manager for an organization that uses Project Server 2013. When you publish a new schedule, a default Project Site is created for you. A team member asks you to create a task list…

The correct answer is C. In your Project Site, open the task list and add the tasks to the Timeline for management to. See the full explanation below for the reasoning.

Question

You are a project manager for an organization that uses Project Server 2013. When you publish a new schedule, a default Project Site is created for you. A team member asks you to create a task list separately from the schedule. The team member wants to use the list for specific work they need to perform in order to complete one of the assignments in the project schedule. On your Project Site, you have the tasks that they have asked for in a task list. The work being performed by this team member becomes critical to the success of your overall schedule. Management asks for a simple report showing them the task list in an easy-to-read format. You need to implement this request. What should you do?

Options

  • AIn Project Web App (PWA), open the schedule and export the task list to Microsoft Excel.
  • BIn Project Web App (PWA), open the schedule and add the tasks to the Timeline for
  • CIn your Project Site, open the task list and add the tasks to the Timeline for management to
  • DIn your Project Site, open the task list and export it to Microsoft Excel.

How the community answered

(40 responses)
  • A
    13% (5)
  • B
    8% (3)
  • C
    78% (31)
  • D
    3% (1)