Microsoft
74-344 · Question #31
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. You notice that some projects have been published with incorrect dat a. You and the…
The correct answer is C. Create a new workflow that automates all of the requirements. See the full explanation below for the reasoning.
Question
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. You notice that some projects have been published with incorrect dat a. You and the project managers spend a lot of time correcting the data problems. You need to implement a new project creation process which does not affect the projects that are already created and which allows you to perform the following actions:
- Review the project data after the project managers create the
projects.
- Send the projects back to the project managers if you find incorrect
data so that they can make the appropriate corrections.
- Repeat the data verification process unless the data does not have
any errors.
- Publish a project only when all of its data is correctly completed.
What should you do?
Options
- AInstruct the project managers to include a task named project review every time they create
- BInstruct the project managers to send you an email every time they create a project they
- CCreate a new workflow that automates all of the requirements.
- DCreate a Published event handler that automates all of the requirements for this enterprise
How the community answered
(34 responses)- A9% (3)
- B18% (6)
- C71% (24)
- D3% (1)