Question
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. You review your organization's issue management process. You need to implement a new issue management process that meets the following requirements: - All issues for future projects need to be associated with a source. - Source values are either Internal or External. What should you do?
Options
- AInstruct the users to attach a text file with the source information every time they create a
- BInstruct the users to write the information about the source into the description field every
- CAdd a new enterprise custom field named Source with an associated lookup table which
- DGo to a Project Site, and customize the issue list by including a new column to allow a value