nerdexam
Microsoft

70-498 · Question #6

You are utilizing the Microsoft Solution Framework (MSF) for Agile Software Development 6.0 process template. You need to track progress for the current sprint. Which three actions should you…

The correct answer is A. Review team capacity. C. Review the task board. E. From the project portal, review the Iteration Backlog spreadsheet. See the full explanation below for the reasoning.

Question

You are utilizing the Microsoft Solution Framework (MSF) for Agile Software Development 6.0 process template. You need to track progress for the current sprint. Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

Options

  • AReview team capacity.
  • BFrom the Product Backlog view of the current sprint, review the By Work capacity bars for
  • CReview the task board.
  • DReview the burndown chart.
  • EFrom the project portal, review the Iteration Backlog spreadsheet.

How the community answered

(48 responses)
  • A
    71% (34)
  • B
    10% (5)
  • D
    19% (9)

Community Discussion

No community discussion yet for this question.

Full 70-498 Practice