You are using the Microsoft Visual Studio Scrum process template. You recently finished a sprint. You need to conduct a retrospective meeting prior to planning the next sprint. What should you do?
The correct answer is B. Analyze the previous sprint to identify what the team is going to do differently during the. The Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint. The purpose of the Sprint Retrospective is to: - Inspect how the last Sprint went with regards to people, relationships…
Question
You are using the Microsoft Visual Studio Scrum process template. You recently finished a sprint. You need to conduct a retrospective meeting prior to planning the next sprint. What should you do?
Options
- AAnalyze items in the product backlog for the next sprint.
- BAnalyze the previous sprint to identify what the team is going to do differently during the
- CAnalyze and revise the story points of the work items completed in the previous sprint.
- DDetermine which items have been finished on the previous sprint.
How the community answered
(23 responses)- A4% (1)
- B78% (18)
- C13% (3)
- D4% (1)
Explanation
The Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint. The purpose of the Sprint Retrospective is to: - Inspect how the last Sprint went with regards to people, relationships, process, and tools; - Identify and order the major items that went well and potential improvements; and, - create a plan for implementing improvements to the way the Scrum Team Sprint Retrospectives are used by teams to deliberately improve. Effective Sprint Retrospectives are an important ingredient in helping good teams become great and great teams sustain themselves.