70-498 · Question #95
Historically your IT group has done a poor job of reporting issues and successes to key decision makers in a timely manner, due to incomplete or inconsistent application lifecycle management (ALM)…
The correct answer is C. Cumulative Flow. Kanban teams prefer to use a Cumulative Flow Diagram to visualize work across the entire backlog. Visualizing the backlog in this manner can help to identify bottlenecks in the process. Scrum Teams can also use a Cumulative Flow Diagram. Professional Scrum Development with…
Question
Historically your IT group has done a poor job of reporting issues and successes to key decision makers in a timely manner, due to incomplete or inconsistent application lifecycle management (ALM) practices. You are implementing Scrum as the process framework for new projects. The scrum master will publish daily progress reports to the product owner and key stakeholders. You need to view daily progress and identify if bottlenecks are occurring in the development process. Which report should you use?
Options
- ABug Trends
- BSprint Burndown
- CCumulative Flow
- DRelease Burndown
How the community answered
(67 responses)- A7% (5)
- B3% (2)
- C78% (52)
- D12% (8)
Explanation
Kanban teams prefer to use a Cumulative Flow Diagram to visualize work across the entire backlog. Visualizing the backlog in this manner can help to identify bottlenecks in the process. Scrum Teams can also use a Cumulative Flow Diagram. Professional Scrum Development with Microsoft Visual Studio 2012 p.6