Your development team uses Scrum as its process framework and utilizes the Microsoft Framework (MSF) for Agile Software Development 6.0 process template. A new team member who is new to Scrum…

The correct answer is C. risk and business value of each requirement. In other words, it's more important to deliver business value in the form of working software than to follow a plan. Professional Scrum Development with Microsoft Visual Studio 2012 p.162

Implement process improvement

Question

Your development team uses Scrum as its process framework and utilizes the Microsoft Framework (MSF) for Agile Software Development 6.0 process template. A new team member who is new to Scrum assumes the role of product owner. You need to help the new product owner prioritize the product backlog. Which basis should you suggest the new product owner use for prioritizing the product backlog?

Options

  • Apersonal preference
  • Bestimated cost and effort for each requirement
  • Crisk and business value of each requirement
  • Dtechnical complexity of each requirement

How the community answered

(21 responses)
  • A
    10% (2)
  • B
    14% (3)
  • C
    71% (15)
  • D
    5% (1)

Explanation

In other words, it's more important to deliver business value in the form of working software than to follow a plan. Professional Scrum Development with Microsoft Visual Studio 2012 p.162

Topics

#product backlog#prioritization#product owner#Scrum