70-498 · Question #7

70-498 Question #7: Real Exam Question with Answer & Explanation

The correct answer is C. Have the team decide which user stories to complete within the sprint.. The Sprint is a fixed-length event (30 days or less) in which the Development Team forecasts items from the Product Backlog and develops the items in the Sprint Backlog according to the acceptance criteria and their Definition of "Done." Professional Scrum Development with Micros

Question

You are part of a scrum team that is trying to identify user stories to complete in the next sprint. You and the team need to select user stories for the next sprint. What should you do?

Options

  • AHave the product owner decide which user stories to complete within the sprint.
  • BHave the scrum master decide which user stories to complete within the sprint.
  • CHave the team decide which user stories to complete within the sprint.
  • DOrder the user stories by their story points. Select the top stories based on the team's

Explanation

The Sprint is a fixed-length event (30 days or less) in which the Development Team forecasts items from the Product Backlog and develops the items in the Sprint Backlog according to the acceptance criteria and their Definition of "Done." Professional Scrum Development with Microsoft Visual Studio 2012 p.169