70-498 · Question #7
70-498 Question #7: Real Exam Question with Answer & Explanation
The correct answer is C. Have the team decide which user stories to complete within the sprint.. The Sprint is a fixed-length event (30 days or less) in which the Development Team forecasts items from the Product Backlog and develops the items in the Sprint Backlog according to the acceptance criteria and their Definition of "Done." Professional Scrum Development with Micros
Question
Options
- AHave the product owner decide which user stories to complete within the sprint.
- BHave the scrum master decide which user stories to complete within the sprint.
- CHave the team decide which user stories to complete within the sprint.
- DOrder the user stories by their story points. Select the top stories based on the team's
Explanation
The Sprint is a fixed-length event (30 days or less) in which the Development Team forecasts items from the Product Backlog and develops the items in the Sprint Backlog according to the acceptance criteria and their Definition of "Done." Professional Scrum Development with Microsoft Visual Studio 2012 p.169