The correct answer is A. Team members. In Scrum, work should never be directed or assigned. When creating or updating a task, don't assign it to anyone who doesn't request the work. Professional Scrum Development with Microsoft Visual Studio 2012 p.183
Question
You manage a development team that uses the Microsoft Visual Studio Scrum 2.0 process template. You establish a product backlog, allocate backlog items for a sprint, and define the tasks required to complete the sprint. You need to ensure that the agreed upon work is assigned to team members. Who should be responsible for assigning work to team members?
Options
- ATeam members
- BProduct owner
- CScrum master
- DTeam lead
Explanation
In Scrum, work should never be directed or assigned. When creating or updating a task, don't assign it to anyone who doesn't request the work. Professional Scrum Development with Microsoft Visual Studio 2012 p.183
Community Discussion
No community discussion yet for this question.