Microsoft
70-498 · Question #33
You are using Microsoft Test Manager (MTM) to run an automated test suite with 240 long- running tests. In your test environment, you have set up four client machines to run these tests. You have…
The correct answer is D. In the Test Controller Manager view, change the Weighting property for all four test agents. See the full explanation below for the reasoning.
Question
You are using Microsoft Test Manager (MTM) to run an automated test suite with 240 long- running tests. In your test environment, you have set up four client machines to run these tests. You have assigned the Client role to all four machines. You need to make sure that when you run the test suite, the tests are distributed equally over all four client machines. What should you do?
Options
- AAdd an even amount of RAM to all four machines.
- BIn the Test Controller Manager view, change the distribution property for the test controller
- CIn the Content view, configure the test suite to use all four environments.
- DIn the Test Controller Manager view, change the Weighting property for all four test agents
How the community answered
(36 responses)- A3% (1)
- B8% (3)
- C3% (1)
- D86% (31)
Community Discussion
No community discussion yet for this question.