70-177 · Question #94
You are the program manager for your organization and you are using Microsoft Project Server and master projects to coordinate all of your projects and subprojects as a program. You have several…
The correct answer is A. Cross-project task links. This is an example of a cross-project task link. These links between projects can have ramifications on the project schedule should one project get delayed, the other successor projects also can Answer options D, C, and B are incorrect. These are not the valid Microsoft Project…
Question
You are the program manager for your organization and you are using Microsoft Project Server and master projects to coordinate all of your projects and subprojects as a program. You have several activities in Project NHQ that must be completed before activities in Project HJH can begin. What type of linking can you use to signal this relationship between projects?
Options
- ACross-project task links
- BInternal program links
- CMaster project links
- DMilestone-based links
How the community answered
(48 responses)- A79% (38)
- B13% (6)
- C6% (3)
- D2% (1)
Explanation
This is an example of a cross-project task link. These links between projects can have ramifications on the project schedule should one project get delayed, the other successor projects also can Answer options D, C, and B are incorrect. These are not the valid Microsoft Project Server terms.