70-177 · Question #85
There are three primary baselines in a project. Which one of the following is NOT a baseline that can be captured in Microsoft Project Server?
The correct answer is C. Quality. Quality is not a project management baseline. Scope often serves as the quality baseline as it represents all that the project should deliver. Answer option B is incorrect. Cost is one of the three baselines and it can be kept and measured in Microsoft Project Server. Answer…
Question
There are three primary baselines in a project. Which one of the following is NOT a baseline that can be captured in Microsoft Project Server?
Options
- ASchedule
- BCost
- CQuality
- DScope
How the community answered
(61 responses)- A10% (6)
- B13% (8)
- C74% (45)
- D3% (2)
Explanation
Quality is not a project management baseline. Scope often serves as the quality baseline as it represents all that the project should deliver. Answer option B is incorrect. Cost is one of the three baselines and it can be kept and measured in Microsoft Project Server. Answer option D is incorrect. Scope is a constant baseline; it consists of the project scope statement, work breakdown structure, and the WBS dictionary. Answer option A is incorrect. You can create and maintain a schedule baseline in Microsoft Project
Topics
Community Discussion
No community discussion yet for this question.