70-177 · Question #85

There are three primary baselines in a project. Which one of the following is NOT a baseline that can be captured in Microsoft Project Server?

The correct answer is C. Quality. Quality is not a project management baseline. Scope often serves as the quality baseline as it represents all that the project should deliver. Answer option B is incorrect. Cost is one of the three baselines and it can be kept and measured in Microsoft Project Server. Answer…

Managing Enterprise Project Management (EPM) Components

Question

There are three primary baselines in a project. Which one of the following is NOT a baseline that can be captured in Microsoft Project Server?

Options

  • ASchedule
  • BCost
  • CQuality
  • DScope

How the community answered

(61 responses)
  • A
    10% (6)
  • B
    13% (8)
  • C
    74% (45)
  • D
    3% (2)

Explanation

Quality is not a project management baseline. Scope often serves as the quality baseline as it represents all that the project should deliver. Answer option B is incorrect. Cost is one of the three baselines and it can be kept and measured in Microsoft Project Server. Answer option D is incorrect. Scope is a constant baseline; it consists of the project scope statement, work breakdown structure, and the WBS dictionary. Answer option A is incorrect. You can create and maintain a schedule baseline in Microsoft Project

Topics

#project baselines#schedule baseline#cost baseline#scope baseline