Question
You work as a Project Manager for company.com Inc. You along with your team need to level project resources. One of your team members is concerned about which project he should work on first. Which of the following attributes of the projects will determine which project your team should work on first when resource leveling is done?
Exhibit
Options
- AIt depends upon the tasks that require the project manager to work on the critical path.
- BIt depends upon the project with the nearest defined milestone.
- CIt depends upon the project manager's determination.
- DIt depends upon the project with the highest project priority set.