70-177 · Question #119

You are the Microsoft Project Server administrator for your company. You have been working with your project managers to develop a change control system for their projects. In the change control…

The correct answer is C. Quality. Quality is not a change control area. The four areas of change control that should be documented by your project management change control system are time, cost, scope, and procurement. Answer option D is incorrect. Procurement is one of the four areas of change control. Answer…

Managing Enterprise Project Management (EPM) Components

Question

You are the Microsoft Project Server administrator for your company. You have been working with your project managers to develop a change control system for their projects. In the change control system, you want to provide a method to document any changes from the areas of the project the change stems from. There are, in practical project management, four areas of change control that should be managed by each project manager. Which one of the following is not one of the four areas of change control?

Options

  • AScope
  • BCost
  • CQuality
  • DProcurement

How the community answered

(42 responses)
  • A
    14% (6)
  • B
    10% (4)
  • C
    71% (30)
  • D
    5% (2)

Explanation

Quality is not a change control area. The four areas of change control that should be documented by your project management change control system are time, cost, scope, and procurement. Answer option D is incorrect. Procurement is one of the four areas of change control. Answer option B is incorrect. Cost is one of the four areas of change control. Answer option A is incorrect. Scope is one of the four areas of change control. Exam Questions, Study Guides, Practice Tests. Lead the way to help you pass any IT Certification exams, 100% Pass Guaranteed or Full Refund. Especially Cisco, CompTIA, Citrix, EMC, HP, Oracle, VMware, Juniper, Check Point, LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email addresses listed below. Any problems about IT certification or our products, you could rely upon us, we will give you satisfactory answers in 24 hours.

Topics

#change control#scope management#cost management#project management areas