You work as a Project Manager for BlueSoft Inc. You use Microsoft Office Project 2007 for developing the project schedule. You are assigned the project of remodeling a home. Your project will require
Sign in or unlock 70-177 to reveal the answer and full explanation for question #100. The question stem and answer options stay visible for context.
Question
You work as a Project Manager for BlueSoft Inc. You use Microsoft Office Project 2007 for developing the project schedule. You are assigned the project of remodeling a home. Your project will require electricians to work on multiple tasks. You have five electricians to work on your project, but you are not sure who will be the best for a certain task. Which of the following actions will you perform to estimate the costs without assigning specific people to tasks?
Options
- ACreate a generic resource "Electrician" and assign it to all the individual tasks.
- BCreate a resource pool.
- CCreate a cost resource "Electrician" and assign it to all the individual tasks.
- DCreate a material resource "Electrician" and assign it to all the individual tasks.
Unlock 70-177 to see the answer
You've previewed enough free 70-177 questions. Unlock 70-177 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.