70-177 · Question #54
You have a Project Server 2010 environment. Project managers are receiving task updates from resources in several different formats such as percent of work complete, actual work done, and hours of…
The correct answer is B. Enforce a single progress reporting method. See the full explanation below for the reasoning.
Question
You have a Project Server 2010 environment. Project managers are receiving task updates from resources in several different formats such as percent of work complete, actual work done, and hours of work done per period. You need to ensure that all resources report task status in the same format. What should you do?
Options
- AEnable Single Entry mode.
- BEnforce a single progress reporting method.
- CEdit the My Tasks view.
- DDisable the Allow users to define custom periods for task updates option.
How the community answered
(19 responses)- B84% (16)
- C5% (1)
- D11% (2)