Microsoft
70-177 · Question #55
70-177 Question #55: Real Exam Question with Answer & Explanation
The correct answer is C. Enable Single Entry mode.. See the full explanation below for the reasoning.
Question
You have a Project Server 2010 environment. Project managers report that they are not receiving all the timesheet updates that users are submitting. You need to ensure that the project managers always receive task updates when users submit their timesheets. What should you do?
Options
- ADefine time reporting periods.
- BUse the Timesheet Adjustment feature to modify the timesheets.
- CEnable Single Entry mode.
- DEnable the Import all timesheet line classifications option.
Community Discussion