You have a Project Server 2010 environment. You need to make sure that the work estimates display the demand for your project, but do not affect the availability of your resources. What should you do?

The correct answer is B. Create generic resources and assign them to the project. See the full explanation below for the reasoning.

Question

You have a Project Server 2010 environment. You need to make sure that the work estimates display the demand for your project, but do not affect the availability of your resources. What should you do?

Options

  • ASet the Max Units value for all resources to 0%.
  • BCreate generic resources and assign them to the project.
  • CCreate a budget resource and uncheck the Resource can be leveled check box.
  • DCreate a work resource and uncheck the Resource can be leveled check box.

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    71% (27)
  • C
    16% (6)
  • D
    8% (3)