Question

You have a Project Server 2010 environment. You need to make sure that the work estimates display the demand for your project, but do not affect the availability of your resources. What should you do?

Options

  • ASet the Max Units value for all resources to 0%.
  • BCreate generic resources and assign them to the project.
  • CCreate a budget resource and uncheck the Resource can be leveled check box.
  • DCreate a work resource and uncheck the Resource can be leveled check box.

Unlock 70-177 to see the answer

You've previewed enough free 70-177 questions. Unlock 70-177 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.