70-177 · Question #30
You have a Project Server 2010 environment. You need to configure the resource pool to allow project managers to track travel expenses for tasks. Which type of resource should you create?
The correct answer is A. cost. See the full explanation below for the reasoning.
Question
You have a Project Server 2010 environment. You need to configure the resource pool to allow project managers to track travel expenses for tasks. Which type of resource should you create?
Options
- Acost
- Bwork
- Cbudget material
- Dbudget generic work
How the community answered
(30 responses)- A80% (24)
- B10% (3)
- C7% (2)
- D3% (1)