Microsoft
70-177 · Question #29
You have a Project Server 2010 environment. You need to configure a new category for a resource manager that allows the manager to manage only the current and future resources that are subordinate…
The correct answer is D. Select the They are descendants of the User via RBS option. See the full explanation below for the reasoning.
Question
You have a Project Server 2010 environment. You need to configure a new category for a resource manager that allows the manager to manage only the current and future resources that are subordinate to the manager in the organization chart. You create a new category. What should you do next?
Options
- ASelect each of the resources by name and add them to the category.
- BSelect the All current and future resources in Project Server database option.
- CSelect the They have the same RBS value as the User option.
- DSelect the They are descendants of the User via RBS option.
How the community answered
(46 responses)- A4% (2)
- B2% (1)
- C11% (5)
- D83% (38)
Community Discussion