You have a Project Server 2010 environment. You need to ensure that timesheet managers are notified and project tasks are rescheduled when employees request personal time off in their timesheets…

The correct answer is C. Create a nonworking Administrative Time type and configure it to require approvals. See the full explanation below for the reasoning.

Question

You have a Project Server 2010 environment. You need to ensure that timesheet managers are notified and project tasks are rescheduled when employees request personal time off in their timesheets. What should you do?

Options

  • ACreate a timesheet Line Classification item and name it Personal Time Off.
  • BCreate a timesheet Line Classification item and enter Needs Approval in the description field.
  • CCreate a nonworking Administrative Time type and configure it to require approvals.
  • DCreate a nonworking Administrative Time type and configure it to not require approvals.

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    79% (31)
  • D
    13% (5)