Microsoft
70-177 · Question #52
You have a Project Server 2010 environment. The finance department reports that Task A on Project 123 is out of funding. You need to configure Project Server 2010 so that: - Resources cannot enter…
The correct answer is D. Select the task within the Close Tasks to Update feature and click Publish. See the full explanation below for the reasoning.
Question
You have a Project Server 2010 environment. The finance department reports that Task A on Project 123 is out of funding. You need to configure Project Server 2010 so that:
- Resources cannot enter time on Task A in Project 123.
- The task remains active.
- These changes take effect immediately.
What should you do?
Options
- ASelect the project within the Close Tasks to Update feature and click Submit.
- BSelect the project within the Close Tasks to Update feature and click Publish.
- CSelect the task within the Close Tasks to Update feature and click Submit.
- DSelect the task within the Close Tasks to Update feature and click Publish.
How the community answered
(66 responses)- A5% (3)
- B8% (5)
- C14% (9)
- D74% (49)
Community Discussion
No community discussion yet for this question.