70-177 · Question #51

You have a Project Server 2010 environment. You need to configure a Project Server instance so that only one month of future assignments is displayed on the My Tasks page. You do not need to display…

The correct answer is B. Modify the Near Future Planning Window setting. See the full explanation below for the reasoning.

Question

You have a Project Server 2010 environment. You need to configure a Project Server instance so that only one month of future assignments is displayed on the My Tasks page. You do not need to display all tasks. What should you do?

Options

  • AModify the Tracking Mode to track Hours per Period.
  • BModify the Near Future Planning Window setting.
  • CCreate a custom view.
  • DCreate a custom report.

How the community answered

(27 responses)
  • A
    19% (5)
  • B
    70% (19)
  • C
    7% (2)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.