70-177 · Question #103

70-177 Question #103: Real Exam Question with Answer & Explanation

Sign in or unlock 70-177 to reveal the answer and full explanation for question #103. The question stem and answer options stay visible for context.

Question

How does the Microsoft Project Server calculate slack when you have multiple projects linked together to a master project acting as a program?

Options

  • AMicrosoft Project Server finds the due date of milestones and calculates backwards based on early
  • BMicrosoft Project Server only uses project completion dates to determine when the next project
  • CMicrosoft Project Server calculates slack by subtracting Early Finish from Early start.
  • DMicrosoft Project Server cannot calculate float or slack between linked projects.