How does the Microsoft Project Server calculate slack when you have multiple projects linked together to a master project acting as a program?
Options
- AMicrosoft Project Server finds the due date of milestones and calculates backwards based on early
- BMicrosoft Project Server only uses project completion dates to determine when the next project
- CMicrosoft Project Server calculates slack by subtracting Early Finish from Early start.
- DMicrosoft Project Server cannot calculate float or slack between linked projects.