400-007 · Question #96
400-007 Question #96: Real Exam Question with Answer & Explanation
The correct answer is B: project time frame. In infrastructure design, constraints are boundaries that limit the solution space - they define what is possible rather than what is desirable. Project time frame (B) is a fundamental constraint because delivery deadlines directly dictate the scope and complexity of what can be
Question
Options
- Amonitoring capabilities
- Bproject time frame
- Cstaff experience
- Dcomponent availability
- Etotal cost
Explanation
In infrastructure design, constraints are boundaries that limit the solution space - they define what is possible rather than what is desirable. Project time frame (B) is a fundamental constraint because delivery deadlines directly dictate the scope and complexity of what can be designed and implemented. Total cost (E) is equally fundamental because budget limits govern technology choices, redundancy levels, and overall solution scale. Together, time and cost form two legs of the classic project management triangle (scope, time, cost). The remaining options - monitoring capabilities (A), staff experience (C), and component availability (D) - are important considerations and influencing factors, but they are not classified as primary design constraints in formal design frameworks. They may shape the design but do not act as hard boundaries the way time and cost do.
Community Discussion
No community discussion yet for this question.