A network operations team has a project to develop a network automation solution. The team organizes the project into a series of iterations that break down the large, complex project into smaller…

The correct answer is C. Scrum. Scrum uses iterative development with short sprints, and daily stand-up meetings structured around three questions: what was done yesterday, what is being done today, and what obstacles exist. This matches the described project management approach.

Gathering and Clarifying Requirements

Question

A network operations team has a project to develop a network automation solution. The team organizes the project into a series of iterations that break down the large, complex project into smaller manageable tasks. The team structures its quick daily meetings around three questions:

  • What did I work on yesterday?
  • What am I working on today?
  • Which issues are blocking me?

Which project management methodology is the team using?

Options

  • ALean
  • BWaterfall
  • CScrum
  • DKanban

How the community answered

(30 responses)
  • A
    3% (1)
  • C
    90% (27)
  • D
    7% (2)

Explanation

Scrum uses iterative development with short sprints, and daily stand-up meetings structured around three questions: what was done yesterday, what is being done today, and what obstacles exist. This matches the described project management approach.