400-007 · Question #236

An enterprise plans to evolve from a traditional WAN network to a software-defined WAN network. The existing devices have limited capability when it comes to virtualization. As the migration is…

The correct answer is A. Deploy controllers, deploy SD-WAN edge routers. In the data center, and migrate branch sites. A zero-impact SD-WAN migration requires establishing the control plane and data center hub before touching branch sites to maintain continuous connectivity throughout the transition.

Designing Network Infrastructure

Question

An enterprise plans to evolve from a traditional WAN network to a software-defined WAN network. The existing devices have limited capability when it comes to virtualization. As the migration is carried out, enterprise applications and services must not experience any traffic impact. Which implementation plan can be used to accommodate this during the migration phase?

Options

  • ADeploy controllers, deploy SD-WAN edge routers. In the data center, and migrate branch sites.
  • BMigrate data center WAN routers, migrate branch sites, and deploy SD-WAN edge routers.
  • CMigrate branch sites, migrate data center WAN routers, and deploy controllers.
  • DDeploy SD-WAN edge routers in the data center, deploy controllers, and migrate branch sites

How the community answered

(39 responses)
  • A
    62% (24)
  • B
    8% (3)
  • C
    21% (8)
  • D
    10% (4)

Why each option

A zero-impact SD-WAN migration requires establishing the control plane and data center hub before touching branch sites to maintain continuous connectivity throughout the transition.

ADeploy controllers, deploy SD-WAN edge routers. In the data center, and migrate branch sites.Correct

Deploying controllers first establishes the SD-WAN orchestration and management plane that all edge devices depend on for policy and tunnel establishment. Deploying SD-WAN edge routers in the data center next creates the hub termination point before any branch is migrated, ensuring branches always have a destination to connect to. Migrating branch sites last means each branch is cutover into an already-operational overlay, preventing any traffic impact to enterprise applications.

BMigrate data center WAN routers, migrate branch sites, and deploy SD-WAN edge routers.

Migrating data center WAN routers before SD-WAN edge routers are in place removes the existing hub without a replacement overlay ready, causing a traffic outage for all branches simultaneously.

CMigrate branch sites, migrate data center WAN routers, and deploy controllers.

Migrating branch sites before controllers or data center infrastructure are deployed leaves branches with no SD-WAN control plane or overlay hub, resulting in immediate connectivity loss.

DDeploy SD-WAN edge routers in the data center, deploy controllers, and migrate branch sites

Deploying SD-WAN edge routers before controllers means the edge routers cannot register or receive policies, rendering the edge deployment non-functional until controllers are later added.

Concept tested: SD-WAN phased migration sequence without traffic disruption

Source: https://www.cisco.com/c/en/us/solutions/collateral/enterprise-networks/sd-wan/nb-09-sd-wan-deploy-guide-cte-en.html

Topics

#SD-WAN migration#WAN migration#deployment sequencing#network migration