400-007 · Question #216
Which development model is closely associated with traditional project management?
The correct answer is B. lifecycle model. The lifecycle model (Systems Development Lifecycle) is the sequential, phase-based approach closely associated with traditional waterfall project management.
Question
Which development model is closely associated with traditional project management?
Options
- AAgile model
- Blifecycle model
- Cstatic model
- Devolutionary delivery model
How the community answered
(31 responses)- B94% (29)
- C3% (1)
- D3% (1)
Why each option
The lifecycle model (Systems Development Lifecycle) is the sequential, phase-based approach closely associated with traditional waterfall project management.
The Agile model is associated with iterative and incremental development, not traditional sequential project management.
The lifecycle model, commonly known as the Systems Development Lifecycle (SDLC) or waterfall model, defines distinct sequential phases - such as requirements, design, implementation, testing, and deployment - that must be completed before the next begins. This structured, phase-gate approach is the hallmark of traditional project management. It assumes requirements are well-understood upfront and changes are minimized once a phase is complete.
A static model is not a recognized formal development methodology in traditional or Agile project management frameworks.
The evolutionary delivery model is associated with Agile project management due to its iterative, feedback-driven delivery cycles.
Concept tested: Traditional project management lifecycle model association
Source: https://learn.microsoft.com/en-us/azure/cloud-adoption-framework/plan/sdlc-methodology