nerdexam
CompTIA

220-1102 · Question #188

An administrator has received approval for a change request for an upcoming server deployment. Which of the following steps should be completed NEXT?

The correct answer is A. Perform a risk analysis. Even after a change request receives approval, a formal risk analysis must be performed before implementation begins. Risk analysis identifies potential failure points, rollback procedures, and impact to other systems, ensuring the deployment does not introduce unexpected…

Operational Procedures

Question

An administrator has received approval for a change request for an upcoming server deployment. Which of the following steps should be completed NEXT?

Options

  • APerform a risk analysis.
  • BImplement the deployment.
  • CVerify end user acceptance
  • DDocument the lessons learned.

How the community answered

(27 responses)
  • A
    74% (20)
  • B
    7% (2)
  • C
    4% (1)
  • D
    15% (4)

Explanation

Even after a change request receives approval, a formal risk analysis must be performed before implementation begins. Risk analysis identifies potential failure points, rollback procedures, and impact to other systems, ensuring the deployment does not introduce unexpected outages or vulnerabilities. In structured change management workflows, approval grants authorization to proceed - but the detailed risk assessment and planning work is completed immediately before actual implementation. Implementing without risk analysis (B) skips a critical safeguard. End user acceptance (C) and lessons learned (D) occur after implementation, not before.

Topics

#Change Management#Server Deployment#Risk Analysis#IT Operations

Community Discussion

No community discussion yet for this question.

Full 220-1102 Practice